TRIM SET,CONTROL VALVE,DWG.627-7117,FOR

Material 4300026505 · TRIM SET · Plant 1000

ALong-leadMonitorSlow-moving
Material
4300026505
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
PERMATA INSTRUMEN INTERNASIONAL PT
Lead time
127 d · P80 149 d
Unit price
Rp 35.2M

Recommendation

  • 1.Forecast 0.2 SET/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 0.1.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 149 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
1 / 2
next delivery 02 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 35.2M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 281 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 346.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_LCV-1648B
PP-120B LEVEL CONTROL
A100.12

Lead time and procurement

Lead time 127 ± 93 days (PO history, 3 PO lines) · on-time 47%

PR dateTypeQtyUnit priceDeliveryLead time
11 Sept 2026PR03
Regular replenishment
2Rp 35.5M02 Nov 2026
open
52 d
11 Jan 2026PR03
Regular replenishment
1Rp 34.0M30 Jan 202619 d
18 Jun 2025PR01
Import / long-lead
2Rp 35.2M17 Jan 2026213 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
24 Dec 20251201000032718Corrective