COUPLING,DWG.264-7453,FOR PP-1470A
Material 4300026585 · COUPLING · Plant 1000
CReducePotentially obsolete
- Material
- 4300026585
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 86 d · P80 139 d
- Unit price
- Rp 8.6M (est.)
Recommendation
- 1.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~86 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 1 exceeds the level to keep (0) by 1.
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 809,486/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~44 days.
Installed on 1 functional locations
0 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1470A METHANE PUMP | C | 2 | 3 | 1.05 |
Lead time and procurement
Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_PP-1470A | Replace lamp as per PM finding |
| 04 Mar 2026 | Medium | PX_PP-1470A | Oil leak at PP-1470A bearing housing |
| 17 May 2025 | Medium | PX_PP-1470A | Install cover plate for MCP cracking |
Recent goods issues
Never issued in the 17-month history.