POSITIONER,VALVE,DWG.671-7221,FOR LCV-38
Material 4300026636 · POSITIONER · Plant 1000
- Material
- 4300026636
- Category
- POSITIONER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 95 d · P80 166 d
- Unit price
- Rp 39.9M (est.)
Recommendation
- 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~95 days; expected demand during lead time 0.1.
- 3.A 94.2% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 1 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 49.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~40 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_LCV-386B PP-1598B LEVEL CONTROL | B | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 95 ± 64 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 09 Jan 2026 | 1 | 201000024572 | Corrective |