COUPLING,DWG.967-6797,FOR PP-1348

Material 4300027444 · COUPLING · Plant 1000

CReduceSlow-moving
Material
4300027444
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
BERKAH TEKNIK GLOBAL PT
Lead time
95 d · P80 139 d
Unit price
Rp 25.5M

Recommendation

  • 1.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.1.
  • 3.A 87.2% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 2 exceeds the level to keep (1) by 1.
Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
87.2%
stockout risk now 0%
Unit price
Rp 25.5M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 436 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~44 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1348
CHARGE GAS PUMP
C141.47

Lead time and procurement

Lead time 95 ± 54 days (PO history + category, 1 PO lines) · on-time 31%

PR dateTypeQtyUnit priceDeliveryLead time
07 Feb 2026PR06
Regular replenishment
2Rp 25.5M10 Jun 2026123 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Aug 2026MediumPX_PP-1348Leak from packing
27 Jun 2026MediumPX_PP-1348Replace lamp as per PM finding
08 Sept 2025LowPX_PP-1348PP-1348 high vibration
21 May 2025LowPX_PP-1348Oil leak at PP-1348 bearing housing

Recent goods issues

Posting dateQtyOrderOrder type
22 Jul 20251204000022756Preventive