SLEEVE,SHAFT,DWG.637-6446,FOR PP-1426A
Material 4300028197 · SLEEVE · Plant 1000
BLong-leadReduceSlow-moving
- Material
- 4300028197
- Category
- SLEEVE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (1 of 1 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 134 d · P80 210 d
- Unit price
- Rp 3.7M
Recommendation
- 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~134 days; expected demand during lead time 0.1.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 5 exceeds the level to keep (2) by 3.
- 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
5 / 4
next delivery 11 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.6%
stockout risk now 0%
Unit price
Rp 3.7M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 274 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 87.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1426A CONDENSATE PUMP | B | 1 | 1 | 0.19 |
Lead time and procurement
Lead time 134 ± 55 days (PO history + category, 2 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 04 Sept 2026 | PR10 Other | 1 | Rp 3.7M | 09 Feb 2027 open | 158 d |
| 27 Jul 2026 | PR06 Regular replenishment | 2 | Rp 3.8M | 11 Nov 2026 open | 107 d |
| 13 Nov 2025 | PR03 Regular replenishment | 1 | Rp 3.6M | 24 May 2027 open | 557 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 May 2025 | Medium | PX_PP-1426A | Oil leak at PP-1426A bearing housing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Dec 2025 | 1 | 201000034955 | Corrective |