NOZZLE,SAFETY VALVE,DWG.476-9874,FOR PRV

Material 4300028231 · NOZZLE · Plant 1000

BSafety-criticalLong-leadReduceSlow-moving
Material
4300028231
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
ANUGRAH TEKNOLOGI INTERNASIONAL PT
Lead time
98 d · P80 177 d
Unit price
Rp 48.5M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality B). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~98 days; expected demand during lead time 0.1.
  • 4.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 5.Stock 5 exceeds the level to keep (2) by 3.
  • 6.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle source
On hand / on order
5 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 48.5M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 379 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 384.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 1 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-1223
SAFETY VALVE PP-1612
B410.47

Lead time and procurement

Lead time 98 ± 50 days (PO history + category, 1 PO lines) · on-time 23%

PR dateTypeQtyUnit priceDeliveryLead time
26 Jun 2025PR06
Regular replenishment
2Rp 48.5M23 Jul 202527 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Aug 2025LowPX_PRV-1223Install cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
17 Sept 20251201000003444Corrective