Sparely
DU

TRIM SET,CONTROL VALVE,DWG.137-9702,FOR

Material 4300028421 · TRIM SET · Plant 1000

ALong-leadReduceExcess
Material
4300028421
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
SAMUDRA MESINDO ABADI PT
Lead time
237 d · P80 328 d
Unit price
Rp 134.8M

Recommendation

  • 1.Forecast 1.4 SET/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~237 days; expected demand during lead time 0.9.
  • 3.A 98.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
  • 4.Stock 13 exceeds the level to keep (4) by 9.
  • 5.Long lead time: 80% of deliveries took up to 328 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadLast turnaround used 1Single sourceOpen PO
On hand / on order
13 / 2
next delivery 13 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
98.7%
stockout risk now 0%
Unit price
Rp 134.8M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 52 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LCV-1032
LEVEL CONTROL VALVE
A100.12

Lead time and procurement

Lead time 237 ± 52 days (PO history, 3 PO lines) · on-time 20%

PR dateTypeQtyUnit priceDeliveryLead time
05 May 2026PR03
Regular replenishment
1Rp 126.4M25 Feb 2027
open
296 d
09 Jan 2026PR06
Regular replenishment
1Rp 134.8M13 Dec 2026
open
338 d
07 Aug 2025PR06
Regular replenishment
2Rp 135.4M15 Jun 2026312 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
10 Aug 20261204000013772Preventive
09 Aug 20261204000013772Preventive
14 Dec 20251203000027801Turnaround