SEAL,LABYRINTH,DWG.909-2064,FOR KC-419A

Material 4300028691 · SEAL · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4300028691
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
DUTA SEJAHTERA ABADI PT
Lead time
159 d · P80 213 d
Unit price
Rp 94.6M

Recommendation

  • 1.Forecast 1.8 SET/year: 1.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~159 days; expected demand during lead time 0.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.On hand 2 + on order 2 is at or below the reorder point: order 1 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1 SET
Rp 94.6M · order by 01 Oct 2026
Expected arrival ≈ 159 days
Long-leadSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 05 Jul 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
5
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 94.6M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 264 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_KC-419A
PROPYLENE FAN
A1195.71

Lead time and procurement

Lead time 159 ± 65 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
26 Mar 2026PR03
Regular replenishment
1Rp 97.5M29 Sept 2026187 d
13 Jan 2026PR01
Import / long-lead
2Rp 91.7M05 Jul 2027
open
538 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026HighPY_KC-419AOverhaul
23 Sept 2026MediumPY_KC-419AInspect coupling KC-419A
18 Sept 2026MediumPY_KC-419AInstall scaffolding at KC-419A
31 Aug 2026MediumPY_KC-419AInstall cover plate for MCP cracking
28 Aug 2026MediumPY_KC-419AInstall scaffolding at KC-419A
12 Aug 2026HighPY_KC-419AKC-419A lube oil filter DP high
11 Jul 2026MediumPY_KC-419AKC-419A lube oil filter DP high
09 Jul 2026MediumPY_KC-419AInstall scaffolding at KC-419A
09 Mar 2026MediumPY_KC-419AInstall scaffolding at KC-419A
22 Jan 2026LowPY_KC-419AInspect coupling KC-419A

Recent goods issues

Posting dateQtyOrderOrder type
10 Jan 20261201000008824Corrective