BLADE,ROTOR,DWG.383-3042,FOR KT-447

Material 4300030337 · BLADE · Plant 1000

SReduceSlow-moving
Material
4300030337
Category
BLADE
Base unit
SET
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
181 d · P80 263 d
Unit price
Rp 381.5M (est.)

Recommendation

  • 1.Forecast 3.9 SET/year: 3.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~181 days; expected demand during lead time 1.9.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 29 exceeds the level to keep (0) by 29.
Price estimatedLead time estimated
On hand / on order
29 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 381.5M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 352 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~99 days.

Installed on 1 functional locations

0 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-447
TURBINE FOR KC-447
S3136.24

Lead time and procurement

Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland
14 Jan 2026MediumPX_KT-447Follow up after steam upset KT-447
21 Nov 2025MediumPX_KT-447Leak from packing
19 Nov 2025MediumPX_KT-447Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
14 Oct 20252201000007048Corrective