IMPELLER,DWG.988-5917,FOR PP-1970

Material 4300031186 · IMPELLER · Plant 1000

AReorderNormalBelow reorder point
Material
4300031186
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
184 d · P80 276 d
Unit price
Rp 171.5M

Recommendation

  • 1.Forecast 2.4 EA/year: 1.7 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 0.9.
  • 3.A 99.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.On hand 2 + on order 1 is at or below the reorder point: order 3 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 514.6M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Single sourceOpen POLead time estimated
On hand / on order
2 / 1
next delivery 18 Apr 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.0%
stockout risk now 7%
Unit price
Rp 171.5M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 62 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1970
FEED PUMP
A161.47

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
19 Jan 2026PR04
Regular (other)
1Rp 171.5M18 Apr 2027
open
454 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Jun 2027PX_PP-1970Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Sept 2026HighPX_PP-1970Overhaul PP-1970
09 Jul 2026MediumPX_PP-1970Install scaffolding at PP-1970
13 May 2026LowPX_PP-1970PP-1970 seal leak
04 May 2026MediumPX_PP-1970PP-1970 seal leak
14 Nov 2025EmergencyPX_PP-1970Install scaffolding at PP-1970
24 May 2025MediumPX_PP-1970PP-1970 seal leak

Recent goods issues

Posting dateQtyOrderOrder type
31 Jul 20262201000025825Corrective