IMPELLER,DWG.988-5917,FOR PP-1970
Material 4300031186 · IMPELLER · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4300031186
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- DUTA ENERGI ABADI PT
- Lead time
- 184 d · P80 276 d
- Unit price
- Rp 171.5M
Recommendation
- 1.Forecast 2.4 EA/year: 1.7 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~184 days; expected demand during lead time 0.9.
- 3.A 99.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 4.On hand 2 + on order 1 is at or below the reorder point: order 3 now.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 514.6M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Single sourceOpen POLead time estimated
On hand / on order
2 / 1
next delivery 18 Apr 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.0%
stockout risk now 7%
Unit price
Rp 171.5M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 62 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1970 FEED PUMP | A | 1 | 6 | 1.47 |
Lead time and procurement
Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 19 Jan 2026 | PR04 Regular (other) | 1 | Rp 171.5M | 18 Apr 2027 open | 454 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jun 2027 | PX_PP-1970 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 02 Sept 2026 | High | PX_PP-1970 | Overhaul PP-1970 |
| 09 Jul 2026 | Medium | PX_PP-1970 | Install scaffolding at PP-1970 |
| 13 May 2026 | Low | PX_PP-1970 | PP-1970 seal leak |
| 04 May 2026 | Medium | PX_PP-1970 | PP-1970 seal leak |
| 14 Nov 2025 | Emergency | PX_PP-1970 | Install scaffolding at PP-1970 |
| 24 May 2025 | Medium | PX_PP-1970 | PP-1970 seal leak |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Jul 2026 | 2 | 201000025825 | Corrective |