RING,WEAR,DWG.569-3262,FOR PP-207
Material 4300031645 · RING · Plant 1000
AReduceNon-moving
- Material
- 4300031645
- Category
- RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 92 d · P80 143 d
- Unit price
- Rp 8.2M (est.)
Recommendation
- 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~92 days; expected demand during lead time 0.0.
- 3.A 98.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 3 exceeds the level to keep (1) by 2.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.5%
stockout risk now 0%
Unit price
Rp 8.2M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 75.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-207 INHIBITOR PUMP | A | 1 | 3 | 1.47 |
Lead time and procurement
Lead time 92 ± 40 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 May 2026 | Medium | PX_PP-207 | Leak from packing |
| 01 Nov 2025 | Medium | PX_PP-207 | PP-207 abnormal noise |
| 14 Jun 2025 | Medium | PX_PP-207 | PP-207 high vibration |
Recent goods issues
Never issued in the 17-month history.