SLEEVE,SHAFT,DWG.573-8293,FOR PP-1225B

Material 4300031884 · SLEEVE · Plant 1000

BLong-leadReorderCriticalStockout
Material
4300031884
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
142 d · P80 210 d
Unit price
Rp 11.1M

Recommendation

  • 1.Forecast 2.1 EA/year: 2.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~142 days; expected demand during lead time 0.8.
  • 3.A 98.8% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.On hand 0 + on order 2 is at or below the reorder point: order 8 now.
  • 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
8 EA
Rp 88.6M · order by 01 Oct 2026
Expected arrival ≈ 142 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 31 Jan 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
98.8%
stockout risk now 15%
Unit price
Rp 11.1M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 205 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 151.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1225B
INHIBITOR PUMP
B120.62

Lead time and procurement

Lead time 142 ± 55 days (PO history + category, 1 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR03
Regular replenishment
1Rp 11.1M25 Feb 2027
open
162 d
09 Jul 2025PR05
Project / turnaround
1Rp 11.1M31 Jan 2027
open
571 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
07 Mar 2026EmergencyPX_PP-1225B[MSI-B-26-WTG-155/M] Replace line
25 May 2025MediumPX_PP-1225BPSM25/[MSI-B-25-KAT-363/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
10 Mar 20265202000000182Emergency