SLEEVE,SHAFT,DWG.872-5428,FOR PP-376A

Material 4300034469 · SLEEVE · Plant 1000

CMonitorStockout
Material
4300034469
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
LANGIT INDUSTRI PRATAMA PT
Lead time
120 d · P80 210 d
Unit price
Rp 4.8M

Recommendation

  • 1.Forecast 1.3 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~120 days; expected demand during lead time 0.2.
  • 3.A 98.5% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 3.
Convert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 27 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
3
order qty 2
Service level
98.5%
stockout risk now 0%
Unit price
Rp 4.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 96 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 15.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~67 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-376A
QUENCH OIL PUMP
C110.62

Lead time and procurement

Lead time 120 ± 55 days (PO history + category, 2 PO lines) · on-time 53%

PR dateTypeQtyUnit priceDeliveryLead time
19 Jun 2026PR06
Regular replenishment
2Rp 4.7M27 Oct 2026
open
130 d
08 Jan 2026PR03
Regular replenishment
2Rp 4.8M16 Mar 202667 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Feb 2027PX_PP-376APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Jun 2025LowPX_PP-376APP-376A seal leak

Recent goods issues

Posting dateQtyOrderOrder type
27 Jun 20261201000031263Corrective