TRIM SET,CONTROL VALVE,DWG.118-9476,FOR

Material 4300036414 · TRIM SET · Plant 1000

ALong-leadMonitorStockout
Material
4300036414
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
MEGA TEKNIK MAKMUR PT
Lead time
163 d · P80 236 d
Unit price
Rp 114.1M

Recommendation

  • 1.Forecast 0.6 SET/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~163 days; expected demand during lead time 0.3.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 07 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 114.1M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 251 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 963.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-621
PP-902B OUTLET FLOW
A141.39

Lead time and procurement

Lead time 163 ± 83 days (PO history + category, 1 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
20 Jul 2026PR05
Project / turnaround
1Rp 115.8M19 Mar 2028
open
608 d
15 Apr 2026PR01
Import / long-lead
2Rp 112.4M07 Oct 2026
open
175 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Jun 2026MediumPX_FCV-621Install scaffolding at FCV-621
22 Jan 2026MediumPX_FCV-621Leak from packing
24 Sept 2025LowPX_FCV-621Replace lamp as per PM finding
18 Jul 2025HighPX_FCV-621FCV-621 stuck

Recent goods issues

Posting dateQtyOrderOrder type
23 Jan 20261201000033025Corrective