TRIM SET,CONTROL VALVE,DWG.362-5167,FOR

Material 4300038234 · TRIM SET · Plant 1000

AReduceNon-moving
Material
4300038234
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
159 d · P80 236 d
Unit price
Rp 78.5M (est.)

Recommendation

  • 1.Forecast 0.8 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~159 days; expected demand during lead time 0.7 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 11 exceeds the level to keep (3) by 8.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
11 / 0
no open PO
Today Min / Max
5 / 16
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 118.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-168
PP-769B OUTLET FLOW
A151.82

Lead time and procurement

Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
04 Dec 2026PX_FCV-168Final Element Overhaul; Control Valve0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Sept 2026MediumPX_FCV-168FCV-168 stuck
07 Jul 2026MediumPX_FCV-168FCV-168; small leak at packing
10 May 2026MediumPX_FCV-168Replace lamp as per PM finding
22 Jan 2026MediumPX_FCV-168[MSI-B-26-BHJ-329/M] Replace line
16 May 2025LowPX_FCV-168Painting FCV-168

Recent goods issues

Never issued in the 17-month history.