RING,WEAR,DWG.115-6902,FOR PP-233A

Material 4300038638 · RING · Plant 1000

ALong-leadReorderNormalBelow reorder point
Material
4300038638
Category
RING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
78 d · P80 143 d
Unit price
Rp 3.9M

Recommendation

  • 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~78 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Long lead time: 80% of deliveries took up to 143 days and the fastest seen in its category 59 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 15.4M · order by 01 Oct 2026
Expected arrival ≈ 78 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 4%
Unit price
Rp 3.9M
PO history
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 157 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~59 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-233A
SLOP OIL PUMP
A100.19

Lead time and procurement

Lead time 78 ± 40 days (PO history + category, 2 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
06 Apr 2026PR06
Regular replenishment
1Rp 3.8M21 May 202645 d
26 Oct 2025PR06
Regular replenishment
1Rp 3.9M05 Jan 202671 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
27 Apr 20261201000005782Corrective
26 Apr 20261201000005782Corrective
09 Feb 20261204000029556Preventive