TRIM SET,CONTROL VALVE,DWG.235-7752,FOR

Material 4300038701 · TRIM SET · Plant 1000

ALong-leadMaintainInsurance gap
Material
4300038701
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
160 d · P80 236 d
Unit price
Rp 62.9M

Recommendation

  • 1.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~160 days; expected demand during lead time 0.0.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 20 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 62.9M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-837C
HYDROGEN FLOW CONTROL
A100.11

Lead time and procurement

Lead time 160 ± 83 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
21 Jul 2026PR03
Regular replenishment
2Rp 63.4M20 Dec 2026
open
152 d
26 Aug 2025PR06
Regular replenishment
1Rp 62.3M11 Feb 2026169 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.