TRIM SET,CONTROL VALVE,DWG.648-1083,FOR

Material 4300041030 · TRIM SET · Plant 1000

BLong-leadReduceExcess
Material
4300041030
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
162 d · P80 236 d
Unit price
Rp 247.7M

Recommendation

  • 1.Forecast 1.2 SET/year: 1.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~162 days; expected demand during lead time 0.5.
  • 3.A 84.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
  • 4.Stock 4 exceeds the level to keep (3) by 1.
  • 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
4 / 1
next delivery 30 May 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
84.3%
stockout risk now 1%
Unit price
Rp 247.7M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 106 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 153.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-512A
BY PASS DUCT
B100.08

Lead time and procurement

Lead time 162 ± 83 days (PO history + category, 1 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
04 Feb 2026PR06
Regular replenishment
1Rp 250.3M30 May 2027
open
480 d
19 Dec 2025PR06
Regular replenishment
2Rp 245.2M08 Jun 2026171 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
17 Jun 20263201000011352Corrective