POSITIONER,VALVE,DWG.595-9766,FOR FCV-97
Material 4300041641 · POSITIONER · Plant 1000
CReduceSlow-moving
- Material
- 4300041641
- Category
- POSITIONER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 81 d · P80 166 d
- Unit price
- Rp 52.7M
Recommendation
- 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~81 days; expected demand during lead time 0.1.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 50 exceeds the level to keep (0) by 50.
Convert to Non StockSingle source
On hand / on order
50 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 52.7M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 263 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-970B CONTROL VALVE | C | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 81 ± 64 days (PO history + category, 2 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 17 Mar 2026 | PR01 Import / long-lead | 1 | Rp 52.6M | 15 Jun 2026 | 90 d |
| 17 Jun 2025 | PR03 Regular replenishment | 1 | Rp 52.8M | 18 Jul 2025 | 31 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Jan 2026 | 1 | 201000028568 | Corrective |