SEAL,LABYRINTH,DWG.874-4117,FOR KC-225D

Material 4300044748 · SEAL · Plant 1000

BReorderCriticalStockout
Material
4300044748
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 1.7 SET/year: 1.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~150 days; expected demand during lead time 0.7.
  • 3.A 94.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 378.4M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
94.9%
stockout risk now 30%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 455 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 328.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~71 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-225D
INHIBITOR COMPRESSOR
B192.71

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPX_KC-225DKC-225D lube oil filter DP high
22 Aug 2026LowPX_KC-225DInstall scaffolding at KC-225D
27 Jul 2026LowPX_KC-225DPainting KC-225D
20 Jun 2026MediumPX_KC-225DInspect coupling KC-225D
07 Jun 2026HighPX_KC-225DKC-225D high vibration
14 Mar 2026MediumPX_KC-225DInstall scaffolding at KC-225D
05 Mar 2026LowPX_KC-225DKC-225D lube oil filter DP high
29 Dec 2025LowPX_KC-225DKC-225D high vibration
20 May 2025MediumPX_KC-225DOverhaul

Recent goods issues

Posting dateQtyOrderOrder type
03 Jul 20252201000013587Corrective