Sparely
DU

BEARING,THRUST PAD,DWG.205-4131,FOR KC-2

Material 4300044749 · BEARING · Plant 1000

BReduceNon-moving
Material
4300044749
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 219.3M (est.)

Recommendation

  • 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 21 exceeds the level to keep (0) by 21.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
21 / 0
no open PO
Today Min / Max
10 / 29
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 13.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-225D
INHIBITOR COMPRESSOR
B192.71

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPX_KC-225DKC-225D lube oil filter DP high
22 Aug 2026LowPX_KC-225DInstall scaffolding at KC-225D
27 Jul 2026LowPX_KC-225DPainting KC-225D
20 Jun 2026MediumPX_KC-225DInspect coupling KC-225D
07 Jun 2026HighPX_KC-225DKC-225D high vibration
14 Mar 2026MediumPX_KC-225DInstall scaffolding at KC-225D
05 Mar 2026LowPX_KC-225DKC-225D lube oil filter DP high
29 Dec 2025LowPX_KC-225DKC-225D high vibration
20 May 2025MediumPX_KC-225DOverhaul

Recent goods issues

Never issued in the 17-month history.