SEAT RING,VALVE,DWG.492-3062,FOR FCV-156

Material 4300044846 · SEAT RING · Plant 1000

CMonitorStockout
Material
4300044846
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
130 d · P80 172 d
Unit price
Rp 18.3M

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~130 days; expected demand during lead time 0.1.
  • 3.A 93.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
Single sourceOpen PO
On hand / on order
0 / 2
next delivery 10 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
93.3%
stockout risk now 0%
Unit price
Rp 18.3M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 310 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1562
CAUSTIC FLOW CONTROL
C110.11

Lead time and procurement

Lead time 130 ± 46 days (PO history, 3 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
02 Sept 2026PR03
Regular replenishment
1Rp 17.9M25 Dec 2026
open
114 d
09 Jun 2026PR03
Regular replenishment
1Rp 18.3M10 Dec 2026
open
184 d
14 Mar 2026PR05
Project / turnaround
2Rp 18.8M14 Aug 2026153 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 May 2025LowPX_FCV-1562Overhaul FCV-1562

Recent goods issues

Posting dateQtyOrderOrder type
25 Nov 20251201000029322Corrective