SPRING,SAFETY VALVE,DWG.184-9273,FOR PRV

Material 4300045214 · SPRING · Plant 1000

SSafety-criticalLong-leadReorderCriticalStockout
Material
4300045214
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
144 d · P80 196 d
Unit price
Rp 3.1M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~144 days; expected demand during lead time 0.4.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 5.On hand 0 + on order 3 is at or below the reorder point: order 3 now.
  • 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Proposed purchase requisition
3 EA
Rp 9.2M · order by 01 Oct 2026
Expected arrival ≈ 144 days
Safety-critical (SCE)Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 10 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 3.1M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 296 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 1 functional locations

0 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-1751
SAFETY VALVE PP-1945B
S310.47

Lead time and procurement

Lead time 144 ± 65 days (PO history + category, 2 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
24 Aug 2026PR06
Regular replenishment
1Rp 3.1M18 Jan 2027
open
147 d
30 Jun 2026PR06
Regular replenishment
2Rp 3.0M10 Dec 2026
open
163 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Jul 2025LowPX_PRV-1751PRV-1751 passing

Recent goods issues

Posting dateQtyOrderOrder type
09 Dec 20251201000032472Corrective
21 Jun 20252201000027662Corrective
20 Jun 20251201000027662Corrective