RING,WEAR,DWG.745-9295,FOR PP-1869
Material 4300046137 · RING · Plant 1000
CMonitorSlow-moving
- Material
- 4300046137
- Category
- RING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 150 d · P80 143 d
- Unit price
- Rp 2.8M
Recommendation
- 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~150 days; expected demand during lead time 0.1.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
Single sourceOpen PO
On hand / on order
1 / 3
next delivery 26 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.5%
stockout risk now 0%
Unit price
Rp 2.8M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~59 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_PP-1869 C3 RECYCLE PUMP | C | 1 | 2 | 0.62 |
Lead time and procurement
Lead time 150 ± 40 days (PO history + category, 1 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 07 Apr 2026 | PR03 Regular replenishment | 1 | Rp 2.8M | 24 Feb 2027 open | 323 d |
| 25 Oct 2025 | PR06 Regular replenishment | 2 | Rp 2.7M | 26 Oct 2026 open | 366 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 05 Aug 2026 | Medium | PY_PP-1869 | Install cover plate for MCP cracking |
| 15 May 2025 | High | PY_PP-1869 | PP-1869 seal leak |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 17 May 2025 | 1 | 204000001507 | Preventive |