SPRING,SAFETY VALVE,DWG.601-7012,FOR PRV
Material 4300047163 · SPRING · Plant 1000
SSafety-criticalLong-leadReorderCriticalStockout
- Material
- 4300047163
- Category
- SPRING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 151 d · P80 196 d
- Unit price
- Rp 3.9M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~151 days; expected demand during lead time 0.4.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
- 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Proposed purchase requisition
5 EA
Rp 19.7M · order by 01 Oct 2026
Expected arrival ≈ 151 days
Safety-critical (SCE)Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 35%
Unit price
Rp 3.9M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 2 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.
Installed on 1 functional locations
0 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-718D SAFETY VALVE KC-369B | S | 3 | 4 | 1.75 |
Lead time and procurement
Lead time 151 ± 65 days (PO history + category, 1 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 25 Jan 2026 | PR06 Regular replenishment | 1 | Rp 3.9M | 04 Aug 2026 | 191 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Sept 2026 | Low | PX_PRV-718D | [MSI-B-26-KCJ-360/M] Replace line |
| 14 Sept 2026 | High | PX_PRV-718D | Replace lamp as per PM finding |
| 17 Jul 2026 | Low | PX_PRV-718D | PRV-718D simmering |
| 13 Jun 2025 | Medium | PX_PRV-718D | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Sept 2026 | 1 | 201000017495 | Corrective |