Sparely
DU

SLEEVE,SHAFT,DWG.833-4629,FOR PP-205B

Material 4300047468 · SLEEVE · Plant 1000

BLong-leadReduceSlow-moving
Material
4300047468
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
154 d · P80 210 d
Unit price
Rp 5.8M

Recommendation

  • 1.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~154 days; expected demand during lead time 0.5.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Stock 7 exceeds the level to keep (6) by 1.
  • 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
7 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.7%
stockout risk now 0%
Unit price
Rp 5.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 476 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 226.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-205B
LEAN AMINE PUMP
B151.90

Lead time and procurement

Lead time 154 ± 55 days (PO history + category, 1 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
12 Dec 2025PR05
Project / turnaround
2Rp 5.8M10 Jul 2026210 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Aug 2026MediumPX_PP-205BOil leak at PP-205B bearing housing
05 Dec 2025LowPX_PP-205BPP-205B seal leak
08 Oct 2025MediumPX_PP-205BReplace lamp as per PM finding
07 Oct 2025MediumPX_PP-205BReplace lamp as per PM finding
17 May 2025MediumPX_PP-205BOil leak at PP-205B bearing housing

Recent goods issues

Posting dateQtyOrderOrder type
12 Jun 20252201000010525Corrective