TRIM SET,CONTROL VALVE,DWG.947-5211,FOR
Material 4300047637 · TRIM SET · Plant 1000
BLong-leadMonitorSlow-moving
- Material
- 4300047637
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- B (1 of 1 FuncLocs A/B)
- Supplier
- RAJAWALI SEJAHTERA ABADI PT
- Lead time
- 120 d · P80 236 d
- Unit price
- Rp 227.5M
Recommendation
- 1.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~120 days; expected demand during lead time 0.2.
- 3.A 92.1% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
- 4.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
92.1%
stockout risk now 8%
Unit price
Rp 227.5M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 238 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 98.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~75 days.
Installed on 1 functional locations
1 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1963B BY PASS LINE | B | 4 | 0 | 0.11 |
Lead time and procurement
Lead time 120 ± 83 days (PO history + category, 2 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 21 May 2026 | PR03 Regular replenishment | 1 | Rp 228.9M | 17 Jul 2026 | 57 d |
| 11 Jun 2025 | PR03 Regular replenishment | 2 | Rp 226.0M | 18 Aug 2025 | 68 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Feb 2026 | 2 | 204000003218 | Preventive |