Sparely
DU

RING,WEAR,DWG.359-3516,FOR PP-1744

Material 4300049249 · RING · Plant 1000

CReduceSlow-moving
Material
4300049249
Category
RING
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
CAHAYA ELEKTRIK JAYA PT
Lead time
83 d · P80 143 d
Unit price
Rp 4.8M

Recommendation

  • 1.Forecast 2.4 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior) + 2.1 from the maintenance plan.
  • 2.Lead time ~83 days; expected demand during lead time 0.1.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 4.
  • 4.Stock 11 exceeds the level to keep (4) by 7.
Convert to Stock ItemSingle source
On hand / on order
11 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
4
order qty 3
Service level
99.8%
stockout risk now 0%
Unit price
Rp 4.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 246 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~59 days.

Installed on 1 functional locations

0 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1744
PROPYLENE PUMP
C300.19

Lead time and procurement

Lead time 83 ± 40 days (PO history + category, 1 PO lines) · on-time 47%

PR dateTypeQtyUnit priceDeliveryLead time
06 May 2025PR06
Regular replenishment
2Rp 4.8M30 Jun 202555 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PX_PP-1744Pump overhaul2.15

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
28 Jan 20261206000027131Other maintenance