IMPELLER,DWG.382-5149,FOR PP-1106A

Material 4300049667 · IMPELLER · Plant 1000

CReduceExcess
Material
4300049667
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 1.9 EA/year: 1.2 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 1.3 (incl. 0.7 planned).
  • 3.A 87.6% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 15 exceeds the level to keep (3) by 12.
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
15 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 1
Rec. Max
3
order qty 1
Service level
87.6%
stockout risk now 0%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 4 days ago, 4 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 52.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~105 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1106A
LUBE OIL PUMP
C162.33

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-1106APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_PP-1106AReplace bearing PP-1106A
25 Aug 2026MediumPX_PP-1106APP-1106A high vibration
06 Aug 2026MediumPX_PP-1106AOverhaul PP-1106A
01 Aug 2026LowPX_PP-1106APP-1106A discharge pressure low
19 Jun 2026MediumPX_PP-1106APP-1106A seal leak
14 May 2025MediumPX_PP-1106APSM25/PP-1106A discharge pressure low

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 20261201000010887Corrective