POSITIONER,VALVE,DWG.566-3412,FOR TCV-44

Material 4300050016 · POSITIONER · Plant 1000

CMonitorStockout
Material
4300050016
Category
POSITIONER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
KANTO VALVE SYSTEMS KK
Lead time
93 d · P80 132 d
Unit price
Rp 23.9M

Recommendation

  • 1.Forecast 2.6 EA/year: 2.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~93 days; expected demand during lead time 0.7.
  • 3.A 80.0% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 3.
Single sourceOpen PO
On hand / on order
0 / 1
next delivery 07 Mar 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
3
order qty 3
Service level
80.0%
stockout risk now 20%
Unit price
Rp 23.9M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 115 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 15.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_TCV-441A
HE-275C TEMP CONTROL
C151.83

Lead time and procurement

Lead time 93 ± 74 days (PO history, 3 PO lines) · on-time 29%

PR dateTypeQtyUnit priceDeliveryLead time
31 Aug 2026PR03
Regular replenishment
1Rp 22.5M07 Mar 2027
open
188 d
03 Dec 2025PR06
Regular replenishment
2Rp 23.9M20 Jan 202648 d
18 Sept 2025PR06
Regular replenishment
1Rp 24.1M27 Oct 202539 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPY_TCV-441AReplace lamp as per PM finding
18 May 2026MediumPY_TCV-441AOverhaul TCV-441A
17 May 2026LowPY_TCV-441AOverhaul TCV-441A
05 May 2026LowPY_TCV-441ATCV-441A stuck
19 May 2025LowPY_TCV-441ATCV-441A; small leak at packing

Recent goods issues

Posting dateQtyOrderOrder type
08 Jun 20261201000007891Corrective
08 Jun 20262201000007891Corrective