Sparely
DU

BEARING,JOURNAL,DWG.383-5936,FOR KC-397A

Material 4300051843 · BEARING · Plant 1000

AReduceExcess
Material
4300051843
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 219.3M (est.)

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.2.
  • 3.A 92.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Stock 4 exceeds the level to keep (2) by 2.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
92.5%
stockout risk now 0%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 111 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 254.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-397A
DILUTION STEAM FAN
A110.57

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Jul 2025LowPX_KC-397APainting KC-397A

Recent goods issues

Posting dateQtyOrderOrder type
12 Jun 20262201000021094Corrective