Sparely
DU

TRIM SET,CONTROL VALVE,DWG.446-3534,FOR

Material 4300052029 · TRIM SET · Plant 1000

ALong-leadReduceExcess
Material
4300052029
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
MEGA TEKNIK MAKMUR PT
Lead time
153 d · P80 236 d
Unit price
Rp 86.4M

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~153 days; expected demand during lead time 0.4.
  • 3.A 99.1% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 75 exceeds the level to keep (3) by 72.
  • 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
75 / 2
next delivery 14 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.1%
stockout risk now 0%
Unit price
Rp 86.4M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 12 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1863
BY PASS LINE
A100.11

Lead time and procurement

Lead time 153 ± 83 days (PO history + category, 2 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
14 Aug 2026PR01
Import / long-lead
1Rp 86.4M16 Apr 2028
open
611 d
26 May 2026PR05
Project / turnaround
1Rp 85.7M14 Nov 2026
open
172 d
18 Aug 2025PR06
Regular replenishment
1Rp 87.2M10 Dec 2025114 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
19 Sept 20261201000013046Corrective
24 Sept 20251201000026626Corrective