NOZZLE,SAFETY VALVE,DWG.668-6909,FOR PRV

Material 4300052078 · NOZZLE · Plant 1000

SSafety-criticalLong-leadReorderNormalBelow reorder point
Material
4300052078
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
123 d · P80 159 d
Unit price
Rp 27.8M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~123 days; expected demand during lead time 0.4.
  • 4.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.On hand 1 + on order 1 is at or below the reorder point: order 3 now.
  • 6.Long lead time: 80% of deliveries took up to 159 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Proposed purchase requisition
3 EA
Rp 83.3M · order by 01 Oct 2026
Expected arrival ≈ 123 days
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
1 / 1
next delivery 05 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.7%
stockout risk now 3%
Unit price
Rp 27.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 168 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-1439D
SAFETY VALVE KC-372D
S100.04

Lead time and procurement

Lead time 123 ± 55 days (PO history, 3 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
16 Jul 2026PR03
Regular replenishment
1Rp 27.6M05 Nov 2026
open
112 d
28 Mar 2026PR06
Regular replenishment
1Rp 27.8M08 Jun 202672 d
03 Mar 2026PR06
Regular replenishment
2Rp 29.0M09 Sept 2026190 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
16 Apr 20261201000020104Corrective
15 Apr 20262201000020104Corrective