TRIM SET,CONTROL VALVE,DWG.453-2598,FOR

Material 4300052638 · TRIM SET · Plant 1000

BLong-leadMonitorSlow-moving
Material
4300052638
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
GUNUNG UTAMA LESTARI PT
Lead time
125 d · P80 123 d
Unit price
Rp 28.4M

Recommendation

  • 1.Forecast 0.8 SET/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~125 days; expected demand during lead time 0.3.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Long lead time: 80% of deliveries took up to 123 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 28.4M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 349 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 326.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-899A
TEMPERATURE CONTROL VALVE
B141.83

Lead time and procurement

Lead time 125 ± 69 days (PO history, 3 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
02 Jan 2026PR03
Regular replenishment
2Rp 27.2M01 Apr 202689 d
15 Oct 2025PR06
Regular replenishment
1Rp 28.4M20 Nov 202536 d
10 Aug 2025PR05
Project / turnaround
2Rp 28.7M03 Jan 2026146 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Aug 2026MediumPX_TCV-899AReplace lamp as per PM finding
16 Aug 2026LowPX_TCV-899AReplace lamp as per PM finding
03 Oct 2025MediumPX_TCV-899AOverhaul TCV-899A
30 Jun 2025MediumPX_TCV-899ATCV-899A; small leak at packing

Recent goods issues

Posting dateQtyOrderOrder type
17 Oct 20251201000007633Corrective
15 Oct 20251201000007633Corrective