BEARING,THRUST PAD,DWG.304-4373,FOR KC-7

Material 4300053502 · BEARING · Plant 1000

SMaintainNo stock needed
Material
4300053502
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 219.3M (est.)

Recommendation

  • 1.Forecast 0.4 SET/year: 0.4 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.1.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 6%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 863,951/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~23 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-773A
REFLUX COMPRESSOR
S1259.99

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
23 Aug 2026LowPX_KC-773AKC-773A bearing temp high
10 Aug 2026LowPX_KC-773AKC-773A high vibration
09 Aug 2026MediumPX_KC-773AInspect coupling KC-773A
03 Aug 2026MediumPX_KC-773ALeak from packing
20 Jul 2026MediumPX_KC-773AKC-773A high vibration
13 Jul 2026LowPX_KC-773AKC-773A lube oil filter DP high
07 Jul 2026MediumPX_KC-773AKC-773A lube oil filter DP high
03 Jul 2026MediumPX_KC-773ALeak from packing

Recent goods issues

Never issued in the 17-month history.