COUPLING,DWG.247-6964,FOR KC-773A

Material 4300053508 · COUPLING · Plant 1000

SReduceSlow-moving
Material
4300053508
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 3.1 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~86 days; expected demand during lead time 0.7.
  • 3.A 83.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 4.
  • 4.Stock 13 exceeds the level to keep (4) by 9.
Price estimatedLead time estimated
On hand / on order
13 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
4
order qty 3
Service level
83.7%
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 258 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~44 days.

Installed on 1 functional locations

0 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-773A
REFLUX COMPRESSOR
S4259.99

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
23 Aug 2026LowPX_KC-773AKC-773A bearing temp high
10 Aug 2026LowPX_KC-773AKC-773A high vibration
09 Aug 2026MediumPX_KC-773AInspect coupling KC-773A
03 Aug 2026MediumPX_KC-773ALeak from packing
20 Jul 2026MediumPX_KC-773AKC-773A high vibration
13 Jul 2026LowPX_KC-773AKC-773A lube oil filter DP high
07 Jul 2026MediumPX_KC-773AKC-773A lube oil filter DP high
03 Jul 2026MediumPX_KC-773ALeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
16 Jan 20261201000030989Corrective