BEARING,JOURNAL,DWG.554-2151,FOR KC-513

Material 4300054403 · BEARING · Plant 1000

SMonitorNo stock needed
Material
4300054403
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
GEMILANG REFRAKTORI JAYA PT
Lead time
88 d · P80 127 d
Unit price
Rp 249.1M

Recommendation

  • 1.Forecast 1.4 SET/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~88 days; expected demand during lead time 0.3.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 28%
Unit price
Rp 249.1M
PO history
ML early warning: 0% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 459 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~23 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-513
WASH WATER BLOWER
S1104.42

Lead time and procurement

Lead time 88 ± 40 days (PO history + category, 1 PO lines) · on-time 20%

PR dateTypeQtyUnit priceDeliveryLead time
20 Nov 2025PR03
Regular replenishment
1Rp 249.1M27 May 2026188 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Sept 2026MediumPX_KC-513KC-513 high vibration
07 Sept 2026MediumPX_KC-513Inspect coupling KC-513
05 Sept 2026LowPX_KC-513Inspect coupling KC-513
30 Aug 2026MediumPX_KC-513KC-513 high vibration
12 Jul 2026MediumPX_KC-513Inspect coupling KC-513
20 Jun 2026MediumPX_KC-513KC-513 bearing temp high
11 May 2026MediumPX_KC-513Leak from packing
22 Nov 2025MediumPX_KC-513Leak from packing
15 Sept 2025MediumPX_KC-513KC-513 bearing temp high
26 Jun 2025MediumPX_KC-513Install scaffolding at KC-513

Recent goods issues

Posting dateQtyOrderOrder type
29 Jun 20251201000001965Corrective