SEAT RING,VALVE,DWG.861-7093,FOR FCV-166

Material 4300055048 · SEAT RING · Plant 1000

SMaintainNo stock needed
Material
4300055048
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
85 d · P80 70 d
Unit price
Rp 7.5M

Recommendation

  • 1.Forecast 0.7 EA/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~85 days; expected demand during lead time 0.2.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Single sourceOpen PO
On hand / on order
0 / 2
next delivery 13 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 7.5M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 153 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~65 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1667
LEAN AMINE FLOW CONTROL
S100.11

Lead time and procurement

Lead time 85 ± 37 days (PO history, 3 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
30 Aug 2026PR03
Regular replenishment
2Rp 7.5M13 Oct 2026
open
44 d
05 Apr 2026PR06
Regular replenishment
1Rp 7.5M07 Jun 202663 d
11 Sept 2025PR03
Regular replenishment
2Rp 7.8M25 Nov 202575 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
01 May 20262201000002272Corrective