TRIM SET,CONTROL VALVE,DWG.408-7714,FOR

Material 4300055282 · TRIM SET · Plant 1000

AReduceExcess
Material
4300055282
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
159 d · P80 236 d
Unit price
Rp 78.5M (est.)

Recommendation

  • 1.Forecast 1.9 SET/year: 1.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~159 days; expected demand during lead time 0.8.
  • 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Stock 8 exceeds the level to keep (6) by 2.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
8 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.2%
stockout risk now 0%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 171 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 1 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-529A
RICH AMINE FLOW CONTROL
A272.25

Lead time and procurement

Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Sept 2026MediumPX_FCV-529AInstall scaffolding at FCV-529A
17 May 2026MediumPX_FCV-529AFCV-529A; IA leak from regulator
05 Apr 2026MediumPX_FCV-529ARepair insulation FCV-529A
26 Mar 2026LowPX_FCV-529AFCV-529A passing
23 Jan 2026LowPX_FCV-529AReplace lamp as per PM finding
21 Sept 2025LowPX_FCV-529AFCV-529A; small leak at packing
31 May 2025MediumPX_FCV-529AInstall scaffolding at FCV-529A

Recent goods issues

Posting dateQtyOrderOrder type
13 Apr 20262201000021986Corrective