Sparely
DU

IMPELLER,DWG.464-2602,FOR PP-200A

Material 4300055933 · IMPELLER · Plant 1000

AReorderNormalBelow reorder point
Material
4300055933
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 1.1 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 1 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 102.1M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 101 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 943.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-200A
LEAN AMINE PUMP
A100.19

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Jul 2027PX_PP-200APump overhaul0.72

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
22 Jun 20261205000023512Other maintenance