BEARING,JOURNAL,DWG.770-4901,FOR KC-588

Material 4300056195 · BEARING · Plant 1000

ALong-leadMonitorSlow-moving
Material
4300056195
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
136 d · P80 277 d
Unit price
Rp 235.3M

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~136 days; expected demand during lead time 0.4.
  • 3.A 82.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 277 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
1 / 2
next delivery 19 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
82.4%
stockout risk now 2%
Unit price
Rp 235.3M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 219 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 255.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-588
CAUSTIC FAN
A121.00

Lead time and procurement

Lead time 136 ± 81 days (PO history, 3 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
28 Oct 2025PR05
Project / turnaround
2Rp 247.7M19 Oct 2026
open
356 d
20 Aug 2025PR03
Regular replenishment
2Rp 235.3M01 Jan 2026134 d
31 Jul 2025PR03
Regular replenishment
1Rp 227.9M06 Jan 2026159 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Feb 2026MediumPX_KC-588KC-588 lube oil filter DP high
24 May 2025MediumPX_KC-588Repair insulation KC-588

Recent goods issues

Posting dateQtyOrderOrder type
24 Feb 20262201000021496Corrective