TRIM SET,CONTROL VALVE,DWG.325-6916,FOR
Material 4300057115 · TRIM SET · Plant 1000
CMonitorStockout
- Material
- 4300057115
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- RAJAWALI SEJAHTERA ABADI PT
- Lead time
- 170 d · P80 223 d
- Unit price
- Rp 62.3M
Recommendation
- 1.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~170 days; expected demand during lead time 0.2.
- 3.A 80.1% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
Convert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 4
next delivery 13 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
80.1%
stockout risk now 0%
Unit price
Rp 62.3M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 274 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 14.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1905A C3 RECYCLE FLOW CONTROL | C | 1 | 1 | 0.11 |
Lead time and procurement
Lead time 170 ± 87 days (PO history, 4 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Jul 2026 | PR03 Regular replenishment | 2 | Rp 58.8M | 25 Oct 2026 open | 105 d |
| 01 May 2026 | PR06 Regular replenishment | 1 | Rp 63.4M | 13 Oct 2026 open | 165 d |
| 20 Dec 2025 | PR01 Import / long-lead | 1 | Rp 62.6M | 26 Oct 2026 open | 310 d |
| 27 May 2025 | PR06 Regular replenishment | 1 | Rp 62.0M | 10 Oct 2025 | 136 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 15 May 2025 | Medium | PX_FCV-1905A | PSM25/Painting FCV-1905A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 31 Dec 2025 | 1 | 201000023152 | Corrective |
| 19 Aug 2025 | 1 | 201000026111 | Corrective |