NOZZLE,SAFETY VALVE,DWG.756-9179,FOR PRV

Material 4300058925 · NOZZLE · Plant 1000

SSafety-criticalLong-leadReduceExcess
Material
4300058925
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
130 d · P80 177 d
Unit price
Rp 36.2M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~130 days; expected demand during lead time 0.6.
  • 4.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.Stock 18 exceeds the level to keep (5) by 13.
  • 6.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Safety-critical (SCE)Long-leadConvert to Stock ItemSingle source
On hand / on order
18 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.4%
stockout risk now 0%
Unit price
Rp 36.2M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 83 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-1319D
SAFETY VALVE HE-1277C
S130.90

Lead time and procurement

Lead time 130 ± 50 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
08 Jan 2026PR03
Regular replenishment
1Rp 37.1M18 Jul 2026191 d
08 Jul 2025PR06
Regular replenishment
2Rp 35.4M13 Oct 202597 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 Sept 2026LowPX_PRV-1319DReplace lamp as per PM finding
01 Jul 2026LowPX_PRV-1319DPRV-1319D passing
20 May 2025LowPX_PRV-1319DLeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
10 Jul 20261201000008232Corrective
26 Nov 20252201000014700Corrective