POSITIONER,VALVE,DWG.113-3008,FOR PCV-16

Material 4300060468 · POSITIONER · Plant 1000

CReduceSlow-moving
Material
4300060468
Category
POSITIONER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
79 d · P80 166 d
Unit price
Rp 56.9M

Recommendation

  • 1.Forecast 0.1 EA/year: 0.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~79 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 1 exceeds the level to keep (0) by 1.
Convert to Non StockSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 56.9M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 414 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1602
PRESSURE CONTROL VALVE
C100.08

Lead time and procurement

Lead time 79 ± 64 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
25 Apr 2026PR03
Regular replenishment
2Rp 56.9M25 May 202630 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
13 Aug 20251201000035961Corrective