IMPELLER,DWG.423-2687,FOR PP-490
Material 4300060991 · IMPELLER · Plant 1000
SReduceExcess
- Material
- 4300060991
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 184 d · P80 276 d
- Unit price
- Rp 90.9M
Recommendation
- 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~184 days; expected demand during lead time 0.5.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 139 exceeds the level to keep (0) by 139.
Convert to Non StockSingle sourceOpen POLead time estimated
On hand / on order
139 / 2
next delivery 04 Jan 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 90.9M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 170 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~105 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_PP-490 COOLING WATER PUMP | S | 1 | 6 | 2.33 |
Lead time and procurement
Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Aug 2025 | PR03 Regular replenishment | 2 | Rp 90.9M | 04 Jan 2027 open | 508 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Aug 2026 | Medium | PY_PP-490 | PP-490 high vibration |
| 23 Jan 2026 | High | PY_PP-490 | Replace lamp as per PM finding |
| 13 Dec 2025 | Medium | PY_PP-490 | PP-490 seal leak |
| 07 Nov 2025 | Low | PY_PP-490 | Replace bearing PP-490 |
| 05 Nov 2025 | Low | PY_PP-490 | Oil leak at PP-490 bearing housing |
| 07 May 2025 | Medium | PY_PP-490 | Overhaul PP-490 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 14 Apr 2026 | 1 | 201000010359 | Corrective |
| 23 Jun 2025 | 1 | 201000033281 | Corrective |