IMPELLER,DWG.423-2687,FOR PP-490

Material 4300060991 · IMPELLER · Plant 1000

SReduceExcess
Material
4300060991
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
S (0 of 1 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
184 d · P80 276 d
Unit price
Rp 90.9M

Recommendation

  • 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~184 days; expected demand during lead time 0.5.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 139 exceeds the level to keep (0) by 139.
Convert to Non StockSingle sourceOpen POLead time estimated
On hand / on order
139 / 2
next delivery 04 Jan 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 90.9M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 170 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~105 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-490
COOLING WATER PUMP
S162.33

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
14 Aug 2025PR03
Regular replenishment
2Rp 90.9M04 Jan 2027
open
508 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
08 Aug 2026MediumPY_PP-490PP-490 high vibration
23 Jan 2026HighPY_PP-490Replace lamp as per PM finding
13 Dec 2025MediumPY_PP-490PP-490 seal leak
07 Nov 2025LowPY_PP-490Replace bearing PP-490
05 Nov 2025LowPY_PP-490Oil leak at PP-490 bearing housing
07 May 2025MediumPY_PP-490Overhaul PP-490

Recent goods issues

Posting dateQtyOrderOrder type
14 Apr 20261201000010359Corrective
23 Jun 20251201000033281Corrective