TRIM SET,CONTROL VALVE,DWG.344-2308,FOR
Material 4300061877 · TRIM SET · Plant 1000
ALong-leadReduceNon-moving
- Material
- 4300061877
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 123 d · P80 236 d
- Unit price
- Rp 47.6M
Recommendation
- 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~123 days; expected demand during lead time 0.0.
- 3.A 98.1% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 2 exceeds the level to keep (1) by 1.
- 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 09 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.1%
stockout risk now 0%
Unit price
Rp 47.6M
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 91.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1256 PP-1570A TEMP CONTROL | A | 1 | 4 | 1.40 |
Lead time and procurement
Lead time 123 ± 83 days (PO history + category, 2 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Aug 2026 | PR06 Regular replenishment | 2 | Rp 47.7M | 09 Oct 2026 open | 50 d |
| 27 Mar 2026 | PR06 Regular replenishment | 2 | Rp 47.4M | 24 Jun 2026 | 89 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Jul 2026 | Low | PX_TCV-1256 | TCV-1256; IA leak from regulator |
| 29 Jul 2026 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
| 16 Apr 2026 | Medium | PX_TCV-1256 | Replace lamp as per PM finding |
| 05 May 2025 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
Recent goods issues
Never issued in the 17-month history.