SEAT RING,VALVE,DWG.415-3503,FOR FCV-158

Material 4300063682 · SEAT RING · Plant 1000

ALong-leadReduceNon-moving
Material
4300063682
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
TIRTA SEJAHTERA PERSADA PT
Lead time
115 d · P80 151 d
Unit price
Rp 16.5M

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~115 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 3 exceeds the level to keep (1) by 2.
  • 5.Long lead time: 80% of deliveries took up to 151 days and the fastest seen in its category 65 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
3 / 2
next delivery 20 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 16.5M
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.

Installed on 1 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1588
PP-1325 OUTLET FLOW
A410.11

Lead time and procurement

Lead time 115 ± 61 days (PO history, 3 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
22 Sept 2026PR06
Regular replenishment
2Rp 16.5M20 Dec 2026
open
89 d
24 Mar 2026PR03
Regular replenishment
1Rp 16.0M09 Jun 202677 d
29 Aug 2025PR05
Project / turnaround
1Rp 16.8M10 Mar 2026193 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 May 2025MediumPX_FCV-1588Overhaul FCV-1588

Recent goods issues

Never issued in the 17-month history.