DEMISTER PAD,DWG.751-7240,FOR CL-932

Material 4300064449 · DEMISTER PAD · Plant 1000

ALong-leadReduceSlow-moving
Material
4300064449
Category
DEMISTER PAD
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
CAHAYA LOGAM PRATAMA PT
Lead time
113 d · P80 147 d
Unit price
Rp 55.5M

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~113 days; expected demand during lead time 0.2.
  • 3.A 98.6% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Stock 4 exceeds the level to keep (2) by 2.
  • 5.Long lead time: 80% of deliveries took up to 147 days and the fastest seen in its category 34 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
4 / 2
next delivery 03 Jan 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.6%
stockout risk now 0%
Unit price
Rp 55.5M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 432 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 420.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~34 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_CL-932
RICH AMINE COLUMN
A151.66

Lead time and procurement

Lead time 113 ± 59 days (PO history + category, 1 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
01 Aug 2026PR06
Regular replenishment
2Rp 55.5M03 Jan 2027
open
155 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
31 Aug 2026LowPX_CL-932CL-932 DP high
20 Aug 2026MediumPX_CL-932CL-932 DP high
02 Jul 2026MediumPX_CL-932Inspect CL-932 internal
02 Jun 2026MediumPX_CL-932Install scaffolding at CL-932
31 May 2025MediumPX_CL-932PSM25/Inspect CL-932 internal

Recent goods issues

Posting dateQtyOrderOrder type
26 Jul 20251201000026768Corrective