TRIM SET,CONTROL VALVE,DWG.569-8706,FOR

Material 4300064530 · TRIM SET · Plant 1000

CReduceNon-moving
Material
4300064530
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
159 d · P80 236 d
Unit price
Rp 78.5M (est.)

Recommendation

  • 1.Forecast 0.8 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~159 days; expected demand during lead time 0.7 (incl. 0.7 planned).
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 16 exceeds the level to keep (0) by 16.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
16 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 78.5M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1447
ETHYLENE FLOW CONTROL
C131.39

Lead time and procurement

Lead time 159 ± 83 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
17 Dec 2026PX_FCV-1447Final Element Overhaul; CV0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Aug 2026MediumPX_FCV-1447FCV-1447; IA leak from regulator
30 Nov 2025HighPX_FCV-1447[MSI-B-25-JDZ-246] Permanent repair
14 Jun 2025MediumPX_FCV-1447FCV-1447 passing

Recent goods issues

Never issued in the 17-month history.