DISC,SAFETY VALVE,DWG.215-2077,FOR PRV-1
Material 4300066596 · DISC · Plant 1000
ASafety-criticalLong-leadReduceSlow-moving
- Material
- 4300066596
- Category
- DISC
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- TIRTA SEJAHTERA PERSADA PT
- Lead time
- 95 d · P80 175 d
- Unit price
- Rp 5.8M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 0.7 EA/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~95 days; expected demand during lead time 0.2.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 5.Stock 8 exceeds the level to keep (5) by 3.
- 6.Long lead time: 80% of deliveries took up to 175 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Long-leadConvert to Stock ItemSingle source
On hand / on order
8 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 5.8M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 425 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 468.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-1711 SAFETY VALVE HE-563D | A | 1 | 1 | 0.04 |
Lead time and procurement
Lead time 95 ± 64 days (PO history, 6 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 Dec 2025 | PR03 Regular replenishment | 2 | Rp 5.9M | 04 Feb 2026 | 36 d |
| 28 Nov 2025 | PR06 Regular replenishment | 3 | Rp 6.1M | 27 May 2026 | 180 d |
| 06 Oct 2025 | PR06 Regular replenishment | 1 | Rp 5.7M | 22 Dec 2025 | 77 d |
| 06 Jul 2025 | PR06 Regular replenishment | 2 | Rp 5.8M | 18 Aug 2025 | 43 d |
| 01 Jul 2025 | PR03 Regular replenishment | 1 | Rp 5.8M | 19 Sept 2025 | 80 d |
| 18 May 2025 | PR06 Regular replenishment | 3 | Rp 5.7M | 09 Nov 2025 | 175 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 12 May 2025 | Low | PX_PRV-1711 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 Aug 2025 | 2 | 204000001961 | Preventive |
| 05 Jun 2025 | 1 | 201000019262 | Corrective |
| 04 Jun 2025 | 1 | 201000019262 | Corrective |